During which step would a formal acceptance of Timebox deliverables occur?

  1. KickOff step

  2. Iterative Development

  3. Scheduled review

  4. Closure step

The correct answer is: Closure step

The formal acceptance of Timebox deliverables occurs during the Closure step because this phase is specifically designed to wrap up the work done during a Timebox. In Agile practices, Timeboxes are used to fixedly structure the periods of work, and at the end of each Timebox, deliverables are reviewed and formally accepted by stakeholders. During the Closure step, the team reflects on what was accomplished, ensuring that all deliverables meet the agreed-upon criteria. This is a crucial part of the Agile process because it provides an opportunity for stakeholders to validate that the work meets their expectations and to finalize any outstanding elements. Additionally, the Closure step allows for lessons learned to be documented and improvements to be identified for future iterations, thus enhancing the overall Agile process. Other steps such as KickOff refer to the initial planning and resource allocations, Iterative Development focuses on the ongoing process of creating deliverables through short cycles, and Scheduled review involves assessing work in progress, but it is in the Closure step where formal acceptance is concluded, making it a pivotal moment for completing Timebox deliverables.