Which activities are included in the Deployment phase of DSDM?

  1. Assembly, Review, Test

  2. Review, Test, Deploy

  3. Assembly, Test, Deploy

  4. Assembly, Review, Deploy

The correct answer is: Assembly, Review, Deploy

The Deployment phase of DSDM (Dynamic Systems Development Method) focuses on ensuring that the product is ready for use and is successfully delivered to the customer. The activities included in this phase are essential for finalizing the solution and making it available for operational use. Assembly involves integrating all the components of the product to create a complete solution that can be assessed in its entirety. This is a critical step to ensure that everything fits together as intended and performs its designated functions. Review is the next step, which includes verifying the work completed during the project against the specifications and requirements. This step ensures that the product meets the agreed-upon standards and fulfills the business needs, allowing for any necessary adjustments before deployment. Finally, Deployment is the last activity within this phase, where the finalized product is officially released and handed over to the customer or end-users. This step is crucial as it marks the transition from development to operational use, ensuring that users can access and utilize the product effectively. These activities—Assembly, Review, and Deploy—form a cohesive unit in the Deployment phase, focusing on integrating feedback and ensuring the product is ready to deliver value to users.